3MW Site #1

Al Ain, Abu Dhabi, UAE3 MW
Otvoreno za investicije

O projektu

Test

Životni ciklus

Funding
Building
Partially operational
Fully operational
Filled by miners

Galerija

Uslovi

Procentualno učešće u prihodu od računa za električnu energiju od hostovanih klijenata.
Isplate mesečno, u zavisnosti od stvarnih priliva i uptime-a.
Ne-kastodijalno; sredstva su rezervisana isključivo za CAPEX/OPEX objekta.
Detaljna dokumenta dostupna su nakon KYC odobrenja.

Sažetak projekta

Total Estimated Cost per 3 MW Site
AED 3,299,165
Total for 3 Sites (≈ 9 MW)
AED 9,897,495

Plan realizacije

1
Municipality Site Plan
Test
$100
2
LDN Request
Test 2
$2,000

Mapa puta projekta

1
Mobilization & Civil (Days 1–30)
Site cleaning, leveling, layout; electrical room civil works; contractor mobilization & materials.
2
Electrical Infrastructure (Days 31–70)
Internal cabling, panels, transformer placement, perimeter fencing; worker accommodation.
3
TAQA Inspection & Connection (Days 71–100)
TAQA inspections and direct fee payment; energization; settle contractor milestones.
4
Hydro Integration & Handover (Days 101–120)
Install two hydro containers per site, integrate RO/cooling; civil piping; testing & handover.

Strategija realizacije

Three sites will be executed in parallel with rotating teams to maintain continuous workflow. Since LDN approvals are complete, execution starts directly with civil and electrical works. Each site is targeted for completion within approximately 120 days.

Zaključak

This roadmap reflects the 3 MW per site configuration, TAQA coordination, and commission inclusion, providing a clear and actionable framework for the 9 MW electricity upgradation project. The plan ensures efficient coordination, timely delivery, and scalable readiness for hydro container installation.